A Bill for an Act
Page 1, Line 101Concerning measures to ensure accountability for
Page 1, Line 102large-load data centers.
Bill Summary
(Note: This summary applies to this bill as introduced and does not reflect any amendments that may be subsequently adopted. If this bill passes third reading in the house of introduction, a bill summary that applies to the reengrossed version of this bill will be available at http://leg.colorado.gov.)
The bill creates certain requirements for large-load data centers, which are defined in the bill as:
- A new data center that has a peak load of more than 30 megawatts or multiple new data centers with a collective peak load of more than 60 megawatts; or
- An existing data center that adds a peak load of more than 30 megawatts or multiple existing data centers that add a collective peak load of more than 60 megawatts.
- The operator has either provided an up-front payment or entered into a contract of at least 15 years with the utility, which up-front payment or contract must require the operator to pay for certain infrastructure and resource costs;
- On or after January 1, 2031, the utility has verified that the operator is in compliance with the hourly matching requirement; and
- The utility determines and ensures that the addition of the large-load data center to the utility's system does not negatively affect the utility's ability to provide reliable service to customers or meet applicable clean energy targets or increase the utility's greenhouse gas emissions.
No later than June 30, 2030, the public utilities commission (commission) is required to make a determination on whether 100% hourly matching by large-load data centers is technically and economically feasible. If the commission determines that 100% hourly matching is not technically and economically feasible, the commission must make a determination of the highest percentage of hourly matching by large-load data centers that is technically and economically feasible (hourly matching requirement), which percentage the commission must update on a regular basis.
Beginning January 1, 2031, an operator of a large-load data center (operator) must generate, purchase, or otherwise acquire a quantity of electricity generated from renewable resources necessary to meet 100% of the operator's large-load data center's total annual electricity consumption. An operator must also achieve the hourly matching requirement. An operator must comply with these requirements through a tariff, contract, or program entered into with a utility, one or more power purchase agreements entered into with an independent power producer, or a self-supply of electricity.
An operator must enter into contracts of at least 15 years with a utility to pay for certain infrastructure and resource costs. An operator must also contribute to utility demand-side management programs and comply with certain operational water management and on-site backup generation requirements.
No later than June 30, 2028, and no later than each June 30 thereafter, an operator must report to the department of public health and environment certain information about the large-load data center, including information about the large-load data center's annual electricity and water consumption. The department of public health and environment must compile the information reported and provide a report to the general assembly and commission and make the report publicly available on the department's website.
A utility is prohibited from interconnecting or supplying electricity to a large-load data center unless:
A utility is prohibited from offering economic development rates to large-load data centers and is required to develop and offer demand response programs or flexible connection tariffs to the utility's customers that are operators. A utility is required to solicit and accept voluntary financial contributions from operators to certain utility programs, which contributions must supplement, rather than substitute, the utility's funding of those programs. A utility that is rate-regulated by the commission with customers that are operators is required to describe efforts to comply with the bill in the utility's annual report filed with the commission.
On or before June 30, 2027, the department of local affairs must publish model codes for the development of large-load data centers, which model codes must consider certain best practices. In developing the model codes, the department of local affairs must conduct a robust stakeholder and engagement process and evaluate, update, and review the model codes every 5 years.
With its development permit application for a large-load data center, the person responsible for the initial development of a large-load data center (developer) must submit a site assessment to the local government reviewing the application. A site assessment must include certain components.
If the siting of a large-load data center is proposed in a disproportionately impacted community or if an operator of an existing data center in a disproportionately impacted community plans to expand the data center's peak load such that the data center will become a large-load data center, the developer or operator must undergo a cumulative impacts analysis before the development or expansion begins. The developer or operator is required to contract with a third-party contractor selected by the department of public health and environment to perform the cumulative impacts analysis.
In reviewing a development permit application for a large-load data center that is in a disproportionately impacted community or is proposed to be in a disproportionately impacted community, the applicable local government is required to consider the applicant's cumulative impacts analysis and whether the mitigation strategies described by the applicant are sufficient to avoid any negative impacts identified in the cumulative impacts analysis. Prior to applying for a development permit that is in a disproportionately impacted community or is proposed to be in a disproportionately impacted community, a developer or operator must comply with certain public hearing, notice, and community outreach requirements.
If the siting of a large-load data center is proposed in a disproportionately impacted community or if an operator of an existing data center in a disproportionately impacted community plans to expand the data center's peak load such that the data center will become a large-load data center, the developer or operator must enter into a community benefit agreement with the disproportionately impacted community before the development or expansion begins. The developer is required to consult with the applicable local government and certain coalition groups and consider certain topics during community benefit agreement negotiations.
An operator is required to comply with certain labor standards.
Page 4, Line 1Be it enacted by the General Assembly of the State of Colorado:
Page 4, Line 2SECTION 1. Legislative declaration. (1) The general assembly
Page 4, Line 3finds that:
Page 4, Line 4(a) Colorado and the United States are experiencing rapid and
Page 4, Line 5unprecedented growth in data centers, which presents significant
Page 4, Line 6challenges for electric utilities, the electric grid, regulators, and electricity
Page 4, Line 7consumers statewide;
Page 4, Line 8(b) Absent clear statutory direction and appropriate safeguards,
Page 4, Line 9the costs of serving new large-load data centers may be shifted to
Page 4, Line 10residential, commercial, and other existing ratepayers, increasing
Page 4, Line 11electricity bills and creating financial risk from overbuilt or stranded
Page 4, Line 12generation, transmission, and distribution infrastructure;
Page 4, Line 13(c) At a time when electricity demand is increasing and
Page 4, Line 14affordability is a growing concern for Colorado households, costs to serve
Page 4, Line 15large-load data centers should not shift onto other ratepayers;
Page 4, Line 16(d) Unchecked growth in large-load data centers may increase
Page 4, Line 17reliance on fossil fuel generation, hinder electric utilities' ability to meet
Page 4, Line 18state and utility clean energy and greenhouse gas emission reduction
Page 4, Line 19requirements, and adversely affect public health and disproportionately
Page 4, Line 20impacted communities;
Page 4, Line 21(e) The general assembly has established statewide climate, clean
Page 5, Line 1energy, and emission reduction goals, including a goal of reaching
Page 5, Line 2net-zero emissions by 2050, which require that new electricity demand be
Page 5, Line 3met through prudent planning, investment in zero-emission resources, and
Page 5, Line 4avoidance of unnecessary fossil fuel expansion;
Page 5, Line 5(f) Maintaining affordable electricity for all Coloradans requires
Page 5, Line 6consumer protection guardrails to ensure that large-load data centers bear
Page 5, Line 7the incremental costs of the generation, transmission, and distribution
Page 5, Line 8infrastructure necessary to serve them;
Page 5, Line 9(g) Operators of large-load data centers should help Colorado
Page 5, Line 10meet its clean energy and climate goals and be responsible for paying
Page 5, Line 11their fair share of the costs of new energy infrastructure and grid
Page 5, Line 12investments needed to meet the demand of large-load data centers;
Page 5, Line 13(h) Flexible load and behind-the-meter resources, when designed
Page 5, Line 14and deployed to provide dispatchable capacity, can reduce peak demand,
Page 5, Line 15defer or avoid distribution and transmission system upgrades, and
Page 5, Line 16mitigate ratepayer impacts associated with large-load data center
Page 5, Line 17interconnections;
Page 5, Line 18(i) Managing large-load data center growth should advance
Page 5, Line 19affordability, reliability, and electrification, ensuring that large-load data
Page 5, Line 20center development strengthens, rather than undermines, Colorado's clean
Page 5, Line 21energy transition;
Page 5, Line 22(j) Colorado rivers have experienced severe water stress in recent
Page 5, Line 23years due to overuse and climate change. New large water users like
Page 5, Line 24large-load data centers may threaten Colorado's water supply security and
Page 5, Line 25the state's ability to provide reliable water resources for other critical
Page 5, Line 26water users, including communities, tribal nations, agricultural users,
Page 5, Line 27recreational users, and the environment.
Page 6, Line 1(k) Promoting the efficient and maximum utilization of Colorado's
Page 6, Line 2water resources by large-load data centers through requiring transparency
Page 6, Line 3of use and sourcing and maximizing sustainable and water-smart cooling
Page 6, Line 4technologies can increase communities' resilience to drought and climate
Page 6, Line 5change, reduce the sale of agricultural water rights in response to
Page 6, Line 6increased demand for municipal water use, and protect river flows and
Page 6, Line 7aquifer levels;
Page 6, Line 8(l) Certain information regarding sources and usage of both water
Page 6, Line 9and energy by large-load data centers is critical to decision-making
Page 6, Line 10processes and should be made available to relevant local and state
Page 6, Line 11authorities;
Page 6, Line 12(m) Colorado has experienced decades of population growth that
Page 6, Line 13has resulted in greatly increased pressure on natural resources, including
Page 6, Line 14land, water, and wildlife. The siting and development of new large-load
Page 6, Line 15data centers and associated infrastructure, including on-site generation
Page 6, Line 16resources and other electrical infrastructure, can result in habitat loss and
Page 6, Line 17fragmentation without appropriate measures to avoid, minimize, and
Page 6, Line 18mitigate direct, indirect, and cumulative impacts to wildlife resources.
Page 6, Line 19The siting and development of new large-load data centers must be
Page 6, Line 20balanced with the obligation of the state to protect wildlife resources and
Page 6, Line 21the hunting, fishing, and recreation traditions that they support, which
Page 6, Line 22traditions are an important part of the economy and culture of Colorado.
Page 6, Line 23(n) The cumulative impacts of pollution are even more devastating
Page 6, Line 24for communities of color and low-income communities who bear outsized
Page 6, Line 25environmental burdens due to past and present discriminatory
Page 6, Line 26environmental and land use policies, endure higher health risks from
Page 6, Line 27pollution exposure, experience systemic injustice, and have faced
Page 7, Line 1exclusion from government and industry decision-making and
Page 7, Line 2enforcement efforts; and
Page 7, Line 3(o) Data center development should support Colorado's workforce
Page 7, Line 4and communities by adhering to high labor standards.
Page 7, Line 5(2) It is therefore in the best interests of the state of Colorado to
Page 7, Line 6establish a comprehensive framework for large-load data centers that:
Page 7, Line 7(a) Ensures electricity service that is clean, affordable, and
Page 7, Line 8reliable;
Page 7, Line 9(b) Protects consumers and communities, including
Page 7, Line 10disproportionately impacted communities;
Page 7, Line 11(c) Advances the state's climate and clean energy goals; and
Page 7, Line 12(d) Affirms the authority of the public utilities commission and
Page 7, Line 13local governments to oversee new large-load data center development in
Page 7, Line 14an equitable and responsible manner.
Page 7, Line 15(3) It is the intent of the general assembly that nothing in this act:
Page 7, Line 16(a) Alters the greenhouse gas emission reduction goals and
Page 7, Line 17deadlines established in section 25-7-102 (2)(g), Colorado Revised
Page 7, Line 18Statutes;
Page 7, Line 19(b) Diminishes the air quality control commission's existing
Page 7, Line 20authority to require more than the minimum greenhouse gas emission
Page 7, Line 21reduction goals and deadlines established in section 25-7-102 (2)(g),
Page 7, Line 22Colorado Revised Statutes; or
Page 7, Line 23(c) Prevents state or local authorities from enacting additional
Page 7, Line 24requirements for large-load data centers.
Page 7, Line 25SECTION 2. In Colorado Revised Statutes, add article 2.5 to title
Page 7, Line 2640 as follows:
Page 7, Line 27ARTICLE 2.5
Page 8, Line 1Large-load Data Centers
Page 8, Line 240-2.5-101. Definitions.
Page 8, Line 3As used in this article 2.5, unless the context otherwise
Page 8, Line 4requires:
Page 8, Line 5(1) "Closed-loop cooling system" means a cooling
Page 8, Line 6configuration that operates by recirculating air, water,
Page 8, Line 7refrigerants, or other heat-transfer mediums within sealed or
Page 8, Line 8self-contained equipment to absorb and reject heat without
Page 8, Line 9exposure to the atmosphere or routine evaporative water loss.
Page 8, Line 10(2) "Cumulative impacts" means the incremental effects
Page 8, Line 11that a large-load data center has on the environment,
Page 8, Line 12including effects on air quality, water quality, water resource
Page 8, Line 13availability, climate, noise, odor, wildlife, and public health,
Page 8, Line 14when added to the impacts from other past, present, and
Page 8, Line 15reasonably foreseeable future development of any type on a
Page 8, Line 16disproportionately impacted community.
Page 8, Line 17(3) "Data center" means a facility that:
Page 8, Line 18(a) Houses information technology equipment used for
Page 8, Line 19data processing, data storage, or telecommunications; and
Page 8, Line 20(b) Has the primary function of delivering one or more
Page 8, Line 21information technology services, including:
Page 8, Line 22(I) Providing data storage, processing, and transport
Page 8, Line 23services;
Page 8, Line 24(II) Supporting the delivery of cloud computing services;
Page 8, Line 25(III) Providing network connectivity services; and
Page 8, Line 26(IV) Supporting artificial intelligence, machine learning,
Page 8, Line 27or similar computational services.
Page 9, Line 1(4) "Emergency" means an unplanned and involuntary
Page 9, Line 2interruption of utility electric service or a condition posing an
Page 9, Line 3imminent risk to public health or safety that is documented and
Page 9, Line 4verified by the serving electric utility.
Page 9, Line 5(5) "Hourly matching" means the demonstrated
Page 9, Line 6proportion of a large-load data center's hourly energy usage
Page 9, Line 7met by purchased or generated renewable resources,
Page 9, Line 8represented as a percentage and demonstrated with certified
Page 9, Line 9third-party accounting, as approved by the commission.
Page 9, Line 10(6) "Large-load data center" means:
Page 9, Line 11(a) A data center that begins operation on or after the
Page 9, Line 12effective date of this section:
Page 9, Line 13(I) With a peak load of more than thirty megawatts; or
Page 9, Line 14(II) That is covered by an interconnection agreement that
Page 9, Line 15allows for a peak load of more than thirty megawatts;
Page 9, Line 16(b) Multiple data centers that begin operation on or
Page 9, Line 17after the effective date of this section and that:
Page 9, Line 18(I) Have a collective peak load of more than sixty
Page 9, Line 19megawatts; or
Page 9, Line 20(II) Are covered by an interconnection agreement or
Page 9, Line 21multiple interconnection agreements that allow for a
Page 9, Line 22collective peak load of more than sixty megawatts;
Page 9, Line 23(c) A data center existing before the effective date of this
Page 9, Line 24section that, on or after the effective date of this section:
Page 9, Line 25(I) Adds a peak load of more than thirty megawatts; or
Page 9, Line 26(II) Signs a new interconnection agreement that allows
Page 9, Line 27for adding a peak load of more than thirty megawatts; or
Page 10, Line 1(d) Multiple data centers existing before the effective
Page 10, Line 2date of this section that, on or after the effective date of this
Page 10, Line 3section:
Page 10, Line 4(I) Add a collective peak load of more than sixty
Page 10, Line 5megawatts at multiple data centers; or
Page 10, Line 6(II) Sign a new interconnection agreement that allows
Page 10, Line 7for adding a collective peak load of more than sixty megawatts
Page 10, Line 8at multiple data centers.
Page 10, Line 9(7) "Large-load data center developer" or "developer"
Page 10, Line 10means a person that is responsible for the initial development of
Page 10, Line 11a large-load data center, including the purchase of land and
Page 10, Line 12the construction of infrastructure intended for a large-load
Page 10, Line 13data center.
Page 10, Line 14(8) "Large-load data center operator" or "operator"
Page 10, Line 15means an owner or operator of a large-load data center.
Page 10, Line 16(9) "Local government" means a statutory or home rule
Page 10, Line 17city, town, county, or city and county.
Page 10, Line 18(10) "Multiple data centers" means all data centers that
Page 10, Line 19are:
Page 10, Line 20(a) Located on a single site or on contiguous sites; and
Page 10, Line 21(b) Owned or operated by the same person or by a person
Page 10, Line 22that controls, is controlled by, or is under common control
Page 10, Line 23with the other person.
Page 10, Line 24(11) "Office" means the Colorado energy office created in
Page 10, Line 25section 24-38.5-101.
Page 10, Line 26(12) "Peak load" means the peak power consumption to be
Page 10, Line 27used by a large-load data center, measured in megawatts.
Page 11, Line 1(13) "Power-usage effectiveness" means the total
Page 11, Line 2electricity consumption of a large-load data center divided by
Page 11, Line 3the electricity consumption of information technology
Page 11, Line 4equipment, including computing, storage, and networking
Page 11, Line 5equipment, in the large-load data center on an annual basis,
Page 11, Line 6expressed as a number.
Page 11, Line 7(14) "Renewable energy storage" has the meaning set
Page 11, Line 8forth in section 40-2-124 (1)(a)(VII.5).
Page 11, Line 9(15) "Renewable resource" has the same meaning as
Page 11, Line 10"renewable energy resources" as defined in section 40-2-124
Page 11, Line 11(1)(a)(VII).
Page 11, Line 12(16) "Use by right" means a land use that proceeds under
Page 11, Line 13objective standards set forth in zoning or other local
Page 11, Line 14government laws and that does not have a discretionary
Page 11, Line 15approval process.
Page 11, Line 16(17) "Water-usage effectiveness" means the total water
Page 11, Line 17consumption of a large-load data center, including direct and
Page 11, Line 18indirect water usage, divided by the electricity consumption of
Page 11, Line 19information technology equipment, including computing,
Page 11, Line 20storage, and networking equipment, in the large-load data
Page 11, Line 21center on an annual basis, expressed as liters per
Page 11, Line 22kilowatt-hour.
Page 11, Line 2340-2.5-102. Hourly matching requirements - determination by
Page 11, Line 24commission.
Page 11, Line 25(1) No later than June 30, 2030, the commission shall, in
Page 11, Line 26consultation with the office and the air pollution control
Page 11, Line 27division in the department of public health and environment and
Page 12, Line 1following a nonadjudicatory proceeding with the opportunity
Page 12, Line 2for public input, make a determination on whether
Page 12, Line 3one-hundred-percent hourly matching by large-load data
Page 12, Line 4centers is technically and economically feasible.
Page 12, Line 5(2) If the commission determines that achieving
Page 12, Line 6one-hundred-percent hourly matching by large-load data
Page 12, Line 7centers is not technically and economically feasible, the
Page 12, Line 8commission, in consultation with the office and the air pollution
Page 12, Line 9control division and following a nonadjudicatory proceeding
Page 12, Line 10with the opportunity for public input, shall make a
Page 12, Line 11determination of the highest percentage of hourly matching by
Page 12, Line 12large-load data centers that is technically and economically
Page 12, Line 13feasible.
Page 12, Line 14(3) After the commission determines the highest
Page 12, Line 15percentage of hourly matching by large-load data centers that
Page 12, Line 16is technically and economically feasible, the commission, in
Page 12, Line 17consultation with the office and the air pollution control
Page 12, Line 18division and following a nonadjudicatory proceeding with the
Page 12, Line 19opportunity for public input, shall update this percentage on a
Page 12, Line 20regular basis but no less frequently than every three years
Page 12, Line 21after the date of the most recent determination.
Page 12, Line 22(4) In making a determination under this section, the
Page 12, Line 23commission may consider the role of flexible load, energy
Page 12, Line 24efficiency, distributed energy resources, and virtual power
Page 12, Line 25plants in reducing peak demand and improving utilization of
Page 12, Line 26renewable resources.
Page 12, Line 2740-2.5-103. Large-load data center requirements - utilization
Page 13, Line 1of renewable resources - utility infrastructure and program
Page 13, Line 2contribution obligations - backup generation requirements.
Page 13, Line 3(1) A large-load data center operator shall, beginning
Page 13, Line 4January 1, 2031:
Page 13, Line 5(a) Generate, purchase, or otherwise acquire a quantity
Page 13, Line 6of electricity generated from renewable resources necessary
Page 13, Line 7to meet one hundred percent of the operator's large-load data
Page 13, Line 8center's total annual electricity consumption for each year
Page 13, Line 9that the large-load data center is operational;
Page 13, Line 10(b) Generate, purchase, or otherwise acquire a quantity
Page 13, Line 11of electricity and associated renewable energy credits
Page 13, Line 12generated from renewable resources for the operator's
Page 13, Line 13large-load data center necessary to achieve at least the
Page 13, Line 14highest percentage of hourly matching that the commission
Page 13, Line 15determines is technically and economically feasible for
Page 13, Line 16large-load data centers pursuant to section 40-2.5-102; and
Page 13, Line 17(c) Ensure that the operator's large-load data center
Page 13, Line 18complies with the hourly matching requirement determined by
Page 13, Line 19the commission pursuant to section 40-2.5-102 in effect at the
Page 13, Line 20time that the large-load data center enters into, renews, or
Page 13, Line 21materially amends a power purchase agreement, renewable
Page 13, Line 22energy contract, or commission-approved clean energy tariff
Page 13, Line 23used for compliance with this section.
Page 13, Line 24(2) (a) The renewable resources described in subsection (1)
Page 13, Line 25of this section must be new and incremental resources
Page 13, Line 26deliverable to the electric grid serving the large-load data
Page 13, Line 27center or deliverable directly to the large-load data center.
Page 14, Line 1(b) Any renewable energy credits associated with the
Page 14, Line 2electricity generated from renewable resources used to meet
Page 14, Line 3the requirements described in subsection (1) of this section must
Page 14, Line 4be retired by the large-load data center operator or on behalf
Page 14, Line 5of the large-load data center operator in the year that the
Page 14, Line 6electricity is generated.
Page 14, Line 7(3) A large-load data center operator shall implement its
Page 14, Line 8compliance with the requirements described in subsection (1) of
Page 14, Line 9this section through one of the following or a combination of
Page 14, Line 10the following methods, which must cover all of the operator's
Page 14, Line 11large-load data center's electricity demands:
Page 14, Line 12(a) A tariff, contract, or program entered into with the
Page 14, Line 13utility supplying the large-load data center with electricity;
Page 14, Line 14(b) One or more power purchase agreements entered into
Page 14, Line 15with an independent power producer supplying the large-load
Page 14, Line 16data center with electricity; or
Page 14, Line 17(c) Self-supply of electricity, including behind-the-meter
Page 14, Line 18generation of renewable resources, or renewable energy
Page 14, Line 19storage used to serve the large-load data center's electricity
Page 14, Line 20demands.
Page 14, Line 21(4) Through contracts with utilities of at least fifteen
Page 14, Line 22years, if using utility power supply, a large-load data center
Page 14, Line 23operator shall pay for the following:
Page 14, Line 24(a) All of the costs associated with a utility constructing
Page 14, Line 25or procuring generation, transmission, and distribution
Page 14, Line 26infrastructure necessary to supply the operator's large-load
Page 14, Line 27data center with electricity;
Page 15, Line 1(b) The operator's share of existing generation,
Page 15, Line 2transmission, distribution, and other resources needed to serve
Page 15, Line 3the operator's large-load data center and other energy supply
Page 15, Line 4and operations infrastructure and equipment required to
Page 15, Line 5maintain grid reliability and operational performance for other
Page 15, Line 6customers; and
Page 15, Line 7(c) All of the costs of renewable resource electricity
Page 15, Line 8curtailments and reserve requirements associated with the
Page 15, Line 9operator's renewable resource electricity purchases and of
Page 15, Line 10infrastructure and investments required to maintain grid
Page 15, Line 11service, stability, and reliability due to stress on the electrical
Page 15, Line 12system caused by the operator's large-load data center.
Page 15, Line 13(5) (a) A large-load data center operator shall
Page 15, Line 14contribute to utility demand-side management programs. The
Page 15, Line 15amount of money that the operator is required to contribute
Page 15, Line 16must be based on the large-load data center's total annual
Page 15, Line 17electricity consumption and the cost-recovery mechanisms that
Page 15, Line 18fund the demand-side management programs.
Page 15, Line 19(b) Subsection (5)(a) of this section applies to a large-load
Page 15, Line 20data center operator regardless of whether the electricity is
Page 15, Line 21supplied by a utility or another source as long as the
Page 15, Line 22large-load data center is connected to the utility's system.
Page 15, Line 23(6) A large-load data center operator shall optimize
Page 15, Line 24operational water management through the implementation of
Page 15, Line 25water-efficient technology, as determined by a local
Page 15, Line 26government with jurisdiction over the large-load data center.
Page 15, Line 27(7) (a) (I) On-site backup power serving a large-load data
Page 16, Line 1center must maximize reliance on renewable resources and
Page 16, Line 2renewable energy storage, to the extent technically and
Page 16, Line 3economically feasible.
Page 16, Line 4(II) A large-load data center operator may rely on
Page 16, Line 5on-site, combustion-based backup generation only after
Page 16, Line 6evaluating and deploying noncombustion backup alternatives
Page 16, Line 7to the maximum extent practicable.
Page 16, Line 8(b) If a large-load data center uses one or more on-site
Page 16, Line 9combustion generators for backup generation, the generator
Page 16, Line 10must:
Page 16, Line 11(I) Be limited to use in an emergency and for required
Page 16, Line 12testing and maintenance. The total amount of use for required
Page 16, Line 13testing and maintenance must be for no more than fifty hours
Page 16, Line 14per year.
Page 16, Line 15(II) Not be used for routine peak shaving, economic
Page 16, Line 16dispatch, capacity or ancillary service markets, or any
Page 16, Line 17nonemergency grid support; and
Page 16, Line 18(III) Use nonresettable meters to track operating hours.
Page 16, Line 19(c) If a large-load data center uses one or more on-site
Page 16, Line 20combustion generators powered by fuel oil for backup
Page 16, Line 21generation, the generator must:
Page 16, Line 22(I) Meet or exceed the United States environmental
Page 16, Line 23protection agency's tier 4 final emissions standards for
Page 16, Line 24stationary compression-ignition engines in effect on the
Page 16, Line 25effective date of this section;
Page 16, Line 26(II) Utilize ultra-low sulfur diesel; and
Page 16, Line 27(III) Be equipped with the best available emissions control
Page 17, Line 1technologies to achieve the United States environmental
Page 17, Line 2protection agency's tier 4 final emissions standards for
Page 17, Line 3stationary compression-ignition engines in effect on the
Page 17, Line 4effective date of this section, including diesel particulate
Page 17, Line 5filters and selective catalytic reduction controls, which must
Page 17, Line 6be properly operated and maintained.
Page 17, Line 7(d) If a large-load data center uses one or more on-site,
Page 17, Line 8gas-powered combustion generators for backup generation:
Page 17, Line 9(I) Any stationary spark-ignition engines must meet or
Page 17, Line 10exceed the United States environmental protection agency's
Page 17, Line 11emissions standards for stationary spark-ignition engines in
Page 17, Line 12effect on the effective date of this section;
Page 17, Line 13(II) Any stationary combustion turbines must meet or
Page 17, Line 14exceed the United States environmental protection agency's
Page 17, Line 15emissions standards for stationary combustion turbines in
Page 17, Line 16effect on the effective date of this section; and
Page 17, Line 17(III) The generators must employ the best available
Page 17, Line 18methane leak detection and repair practices and prohibit
Page 17, Line 19routine venting or bypassing of emissions controls.
Page 17, Line 2040-2.5-104. Reporting to the department of public health and
Page 17, Line 21environment.
Page 17, Line 22(1) No later than June 30, 2028, and no later than each
Page 17, Line 23June 30 thereafter, a large-load data center operator shall
Page 17, Line 24report to the department of public health and environment the
Page 17, Line 25following information for the previous calendar year for the
Page 17, Line 26operator's large-load data center:
Page 17, Line 27(a) Total annual electricity consumption;
Page 18, Line 1(b) Peak load;
Page 18, Line 2(c) Total annual electricity supply serving the
Page 18, Line 3large-load data center, disaggregated by:
Page 18, Line 4(I) Electricity purchased from off-site renewable
Page 18, Line 5resources, by source;
Page 18, Line 6(II) Electricity purchased from off-site nonrenewable
Page 18, Line 7resources, by source;
Page 18, Line 8(III) Electricity generated on site from renewable
Page 18, Line 9resources;
Page 18, Line 10(IV) Electricity discharged on site from renewable
Page 18, Line 11energy storage; and
Page 18, Line 12(V) Electricity generated on site from nonrenewable
Page 18, Line 13resources, including combustion-based backup generation;
Page 18, Line 14(d) Hourly consumption of electricity provided for eight
Page 18, Line 15thousand seven hundred sixty hours;
Page 18, Line 16(e) Hourly electricity supply from renewable resources
Page 18, Line 17for eight thousand seven hundred sixty hours;
Page 18, Line 18(f) Total installed capacity of:
Page 18, Line 19(I) On-site renewable resources, by fuel type and in
Page 18, Line 20megawatts;
Page 18, Line 21(II) On-site renewable energy storage capacity, in
Page 18, Line 22megawatts and in megawatt-hours; and
Page 18, Line 23(III) On-site backup generation, by fuel type and in
Page 18, Line 24megawatts;
Page 18, Line 25(g) Total annual hours of operation for each on-site
Page 18, Line 26backup generator, disaggregated by fuel type and by use
Page 18, Line 27category, including for emergency use and use in testing or
Page 19, Line 1maintenance;
Page 19, Line 2(h) Total annual discharge from renewable energy
Page 19, Line 3storage;
Page 19, Line 4(i) Power-usage effectiveness;
Page 19, Line 5(j) Total annual water consumption, including peak water
Page 19, Line 6demand per day, types of cooling technologies employed, and
Page 19, Line 7efforts to improve on-site water efficiency and reuse;
Page 19, Line 8(k) Total water input in cubic meters that includes all
Page 19, Line 9water volumes that enter the large-load data center that are
Page 19, Line 10used for the functions of the large-load data center;
Page 19, Line 11(l) The sources of water for the large-load data center,
Page 19, Line 12including municipal water supply, groundwater, and surface
Page 19, Line 13water, and whether water from the sources is potable or
Page 19, Line 14reclaimed. If the large-load data center utilizes more than one
Page 19, Line 15water source, the operator shall provide information regarding
Page 19, Line 16water usage from each source as a percentage of total water
Page 19, Line 17usage.
Page 19, Line 18(m) Water-usage effectiveness; and
Page 19, Line 19(n) The total amount of incentives or subsidies received by
Page 19, Line 20the large-load data center operator from local governments,
Page 19, Line 21economic development organizations, or other entities for the
Page 19, Line 22development of the large-load data center.
Page 19, Line 23(2) Notwithstanding section 24-1-136 (11)(a)(I), the
Page 19, Line 24department of public health and environment shall compile the
Page 19, Line 25information reported to the department pursuant to subsection
Page 19, Line 26(1) of this section and provide an annual report to the general
Page 19, Line 27assembly and the commission and make the annual report
Page 20, Line 1publicly available on the department's website.
Page 20, Line 240-2.5-105. Utility requirements - definition.
Page 20, Line 3(1) As used in this section, unless the context otherwise
Page 20, Line 4requires, "utility" includes:
Page 20, Line 5(a) A cooperative electric association, as defined in
Page 20, Line 6section 40-9.5-102 (1);
Page 20, Line 7(b) A municipal electric utility; and
Page 20, Line 8(c) A wholesale electric cooperative, as defined in section
Page 20, Line 940-2-134 (2).
Page 20, Line 10(2) (a) A utility shall not interconnect or supply
Page 20, Line 11electricity to a large-load data center unless the large-load
Page 20, Line 12data center operator has either first provided an up-front
Page 20, Line 13payment or entered into a contract of at least fifteen years
Page 20, Line 14with the utility, which up-front payment or contract must
Page 20, Line 15require the operator to pay for the following:
Page 20, Line 16(I) All of the costs associated with the utility
Page 20, Line 17constructing or procuring generation, transmission, and
Page 20, Line 18distribution infrastructure necessary to supply the operator's
Page 20, Line 19large-load data center with electricity;
Page 20, Line 20(II) The operator's share of existing generation,
Page 20, Line 21transmission, distribution, and other resources needed to serve
Page 20, Line 22the operator's large-load data center and other energy supply
Page 20, Line 23and operations infrastructure and equipment required to
Page 20, Line 24maintain grid reliability and operational performance for the
Page 20, Line 25utility's other customers; and
Page 20, Line 26(III) All of the costs of renewable resource electricity
Page 20, Line 27curtailments and reserve requirements associated with the
Page 21, Line 1operator's renewable resource electricity purchases and the
Page 21, Line 2costs of infrastructure and investments required to maintain
Page 21, Line 3grid service, stability, and reliability due to stress on the
Page 21, Line 4electrical system caused by the operator's large-load data
Page 21, Line 5center.
Page 21, Line 6(b) In establishing cost allocation in electricity rates, a
Page 21, Line 7utility shall account for cost causation for large-load data
Page 21, Line 8centers across all hours of the year.
Page 21, Line 9(c) A utility may require a large-load data center in the
Page 21, Line 10utility's service territory with a self-supply of electricity to
Page 21, Line 11enter into a contract or provide up-front payments for the
Page 21, Line 12costs that the large-load data center imposes on the utility to
Page 21, Line 13provide backup power.
Page 21, Line 14(3) A utility shall not interconnect or supply electricity
Page 21, Line 15to a large-load data center on or after January 1, 2031, unless
Page 21, Line 16it has verified that the large-load data center operator is in
Page 21, Line 17compliance with the hourly matching requirement determined
Page 21, Line 18by the commission pursuant to section 40-2.5-102.
Page 21, Line 19(4) A utility shall not offer economic development rates
Page 21, Line 20pursuant to section 40-3-104.3 to large-load data centers.
Page 21, Line 21(5) (a) A utility shall develop and offer at least one of
Page 21, Line 22the following to the utility's customers that are large-load
Page 21, Line 23data center operators:
Page 21, Line 24(I) One or more demand response programs, which
Page 21, Line 25programs must not allow the use of diesel generators, that
Page 21, Line 26encourage large-load data center operators to significantly
Page 21, Line 27reduce the power demand of the operator's large-load data
Page 22, Line 1center during peak periods through load-shifting, battery
Page 22, Line 2storage, uninterruptible power supply, or on-site or
Page 22, Line 3zero-emissions backup generation; or
Page 22, Line 4(II) Flexible connection tariffs or other tariffs that
Page 22, Line 5encourage or require large-load data center operators to
Page 22, Line 6significantly reduce the power demand of the operator's
Page 22, Line 7large-load data center during peak periods.
Page 22, Line 8(b) A utility may:
Page 22, Line 9(I) Provide expedited interconnection to a large-load
Page 22, Line 10data center operator that commits to flexible interconnection
Page 22, Line 11or commits to achieving at least eighty-percent hourly
Page 22, Line 12matching of renewable resources with the large-load data
Page 22, Line 13center's electricity consumption by 2030; and
Page 22, Line 14(II) Require flexible interconnection as a condition for
Page 22, Line 15interconnection of a large-load data center.
Page 22, Line 16(c) An interconnection agreement between a utility and
Page 22, Line 17a large-load data center operator must include a requirement
Page 22, Line 18for an up-front payment or security by the large-load data
Page 22, Line 19center operator and significant monthly demand charges,
Page 22, Line 20unless the operator participates in a flexible interconnection
Page 22, Line 21tariff or program that provides system benefits for which
Page 22, Line 22corresponding charges may be reduced without creating
Page 22, Line 23cross-subsidization by other customer classes.
Page 22, Line 24(6) (a) A utility shall not interconnect or supply
Page 22, Line 25electricity to a large-load data center unless the utility has
Page 22, Line 26determined and ensures that the addition of the large-load
Page 22, Line 27data center to the utility's system:
Page 23, Line 1(I) Does not negatively affect the utility's ability to
Page 23, Line 2provide reliable electric service to existing customers;
Page 23, Line 3(II) Does not negatively affect the utility's ability to
Page 23, Line 4comply with section 25-7-105 or the rules adopted pursuant to
Page 23, Line 5section 25-7-105 or the utility's achievement of the clean energy
Page 23, Line 6targets described in section 40-2-125.5 (3), if applicable, or other
Page 23, Line 7applicable clean energy and emissions targets, including
Page 23, Line 8economy-wide targets; and
Page 23, Line 9(III) Does not increase the utility's greenhouse gas
Page 23, Line 10emissions for the fifteen years after the addition of the
Page 23, Line 11large-load data center, compared to projected greenhouse gas
Page 23, Line 12emissions by the utility without the addition of the large-load
Page 23, Line 13data center.
Page 23, Line 14(b) Any costs incurred by a utility in making the
Page 23, Line 15determination described in subsection (6)(a) of this section must
Page 23, Line 16be borne by the large-load data center seeking interconnection.
Page 23, Line 17(7) (a) A utility shall solicit and accept, if offered by a
Page 23, Line 18large-load data center operator, voluntary financial
Page 23, Line 19contributions to the utility's income-qualified energy efficiency,
Page 23, Line 20electrification, demand response, distributed energy resources,
Page 23, Line 21or virtual power plant programs.
Page 23, Line 22(b) If a large-load data center operator provides a
Page 23, Line 23voluntary financial contribution, the voluntary financial
Page 23, Line 24contribution must supplement, rather than substitute, the
Page 23, Line 25utility's funding of the programs described in subsection (7)(a) of
Page 23, Line 26this section. A voluntary financial contribution by a large-load
Page 23, Line 27data center operator is not subject to cost-effectiveness
Page 24, Line 1testing and shall not be counted as part of utility expenditures
Page 24, Line 2relative to any budget caps for the programs described in
Page 24, Line 3subsection (7)(a) of this section.
Page 24, Line 4(c) A utility that receives a voluntary financial
Page 24, Line 5contribution from one or more large-load data center
Page 24, Line 6operators shall include information about the voluntary
Page 24, Line 7financial contribution, including the amount received, how the
Page 24, Line 8money was used, and any demonstrated customer or grid
Page 24, Line 9benefits, in the utility's annual energy efficiency and
Page 24, Line 10electrification reports.
Page 24, Line 11(8) (a) A utility rate-regulated by the commission with one
Page 24, Line 12or more customers that are large-load data center operators
Page 24, Line 13shall describe the utility's efforts to comply with this section
Page 24, Line 14in the utility's annual report filed with the commission.
Page 24, Line 15(b) A utility rate-regulated by the commission with one or
Page 24, Line 16more customers that are large-load data center operators
Page 24, Line 17shall provide monthly reporting to the commission on the
Page 24, Line 18following:
Page 24, Line 19(I) Number and capacity of new large-load data center
Page 24, Line 20interconnection requests;
Page 24, Line 21(II) Number and capacity of new large-load data center
Page 24, Line 22interconnection requests rejected by the utility or withdrawn;
Page 24, Line 23(III) Total capacity of new large-load data center
Page 24, Line 24interconnection requests in queue with a signed interconnection
Page 24, Line 25agreement; and
Page 24, Line 26(IV) Number and capacity of new large-load data center
Page 24, Line 27customer interconnections completed and in operation.
Page 25, Line 1(9) Nothing in this section prohibits the commission from
Page 25, Line 2adopting a tariff for large-load data center operators, or a
Page 25, Line 3subset of large-load data center operators, that includes more
Page 25, Line 4stringent requirements than this section.
Page 25, Line 540-2.5-106. Model local codes by the department of local
Page 25, Line 6affairs - site assessments.
Page 25, Line 7(1) (a) On or before June 30, 2027, the department of local
Page 25, Line 8affairs shall publish model codes for the development of
Page 25, Line 9large-load data centers. The model codes must consider, at a
Page 25, Line 10minimum, best practices for the following:
Page 25, Line 11(I) Updating local zoning laws to respond to the
Page 25, Line 12proliferation of large-load data centers;
Page 25, Line 13(II) Avoiding and mitigating potential new impacts to
Page 25, Line 14residents from noise, light, air, electromagnetic fields, and
Page 25, Line 15other sources of pollution, including from on-site backup
Page 25, Line 16generation;
Page 25, Line 17(III) Updating public engagement processes related to
Page 25, Line 18large-load data center development;
Page 25, Line 19(IV) Establishing water and land use policy mechanisms
Page 25, Line 20and development review processes to align large water user
Page 25, Line 21development with sustainable water management, including
Page 25, Line 22water-related siting considerations, the use of nonpotable
Page 25, Line 23supplies and on-site water reuse, and water efficiency tools and
Page 25, Line 24technology. The policy mechanisms and development review
Page 25, Line 25processes may include:
Page 25, Line 26(A) Establishing additional requirements for large water
Page 25, Line 27users;
Page 26, Line 1(B) Implementing water demand offset or net neutral
Page 26, Line 2growth policies;
Page 26, Line 3(C) Adopting water allocation policies with quantified
Page 26, Line 4water resources for water intensive industrial growth;
Page 26, Line 5(D) Requiring conservation plans with identified
Page 26, Line 6efficiency and reuse best practices in water service applications;
Page 26, Line 7or
Page 26, Line 8(E) Developing reporting guidance and templates for
Page 26, Line 9water and waste use streams;
Page 26, Line 10(V) Requiring a large-load data center developer to
Page 26, Line 11prove to a local government in its development permit
Page 26, Line 12application how the large-load data center project will fit
Page 26, Line 13within local government strategic planning and laws with
Page 26, Line 14clear and transparent timelines, plans, and accountability
Page 26, Line 15measures;
Page 26, Line 16(VI) Creating and implementing community benefit
Page 26, Line 17agreements, including recommendations for public engagement;
Page 26, Line 18and
Page 26, Line 19(VII) Implementing reporting requirements to local
Page 26, Line 20governments and impacted communities related to on-site fossil
Page 26, Line 21fuel generation.
Page 26, Line 22(b) The department of local affairs shall conduct a
Page 26, Line 23robust stakeholder and engagement process in developing the
Page 26, Line 24model codes described in subsection (1)(a) of this section,
Page 26, Line 25including engagement with:
Page 26, Line 26(I) State agencies, including the air pollution control
Page 26, Line 27division and the water quality control division in the
Page 27, Line 1department of public health and environment, the commission,
Page 27, Line 2the office, and the department of natural resources;
Page 27, Line 3(II) Colorado consumer protection organizations;
Page 27, Line 4(III) Statewide labor and trade associations;
Page 27, Line 5(IV) Statewide energy and climate organizations;
Page 27, Line 6(V) Colorado agricultural interests;
Page 27, Line 7(VI) Disproportionately impacted communities;
Page 27, Line 8(VII) Large-load data center developers;
Page 27, Line 9(VIII) Large-load data center operators;
Page 27, Line 10(IX) Tribal governments;
Page 27, Line 11(X) Municipal water utilities; and
Page 27, Line 12(XI) Municipal electric utilities and cooperative electric
Page 27, Line 13associations.
Page 27, Line 14(c) The department of local affairs shall evaluate,
Page 27, Line 15update, and review the model codes described in subsection (1)(a)
Page 27, Line 16of this section every five years after the date of the publishing
Page 27, Line 17of the model codes.
Page 27, Line 18(2) With its development permit application for a
Page 27, Line 19large-load data center, a large-load data center developer
Page 27, Line 20shall submit a site assessment to the local government
Page 27, Line 21reviewing the development permit application. A site assessment
Page 27, Line 22must include descriptions of:
Page 27, Line 23(a) Anticipated total water footprint, including direct
Page 27, Line 24and indirect water usage and total water input in cubic meters;
Page 27, Line 25(b) Planned water sources, including information
Page 27, Line 26regarding water usage from each source as a percentage of
Page 27, Line 27total water usage;
Page 28, Line 1(c) Anticipated on-site air emissions, including emissions of
Page 28, Line 2greenhouse gases; toxic air contaminants, as defined in section
Page 28, Line 325-7-109.5 (1)(i); and criteria pollutants, as defined in section
Page 28, Line 443-1-128 (2)(b);
Page 28, Line 5(d) Any potential impacts on agricultural, historic, and
Page 28, Line 6cultural resources within the local government's jurisdiction;
Page 28, Line 7(e) Efforts to locate backup generation and other
Page 28, Line 8sources of air, noise, and light pollution as far as reasonably
Page 28, Line 9possible from residences, schools, and health clinics; and
Page 28, Line 10(f) A description of initial and ongoing opportunities for
Page 28, Line 11public engagement.
Page 28, Line 12(3) Nothing in this section establishes, alters, impairs, or
Page 28, Line 13negates the ability of a local government to regulate land use
Page 28, Line 14related to large-load data centers; except that a local
Page 28, Line 15government shall not allow large-load data centers to be
Page 28, Line 16zoned as a use by right.
Page 28, Line 1740-2.5-107. Disproportionately impacted communities -
Page 28, Line 18cumulative impacts analysis - review of development permit
Page 28, Line 19application by local governments - community engagement -
Page 28, Line 20community benefit agreements.
Page 28, Line 21(1) (a) If the siting of a large-load data center is proposed
Page 28, Line 22in a disproportionately impacted community or if an operator of
Page 28, Line 23a data center in a disproportionately impacted community that
Page 28, Line 24exists before the effective date of this section plans to expand
Page 28, Line 25the data center's peak load such that the data center will
Page 28, Line 26become a large-load data center, the large-load data center
Page 28, Line 27developer or large-load data center operator, as applicable,
Page 29, Line 1shall undergo a cumulative impacts analysis before the
Page 29, Line 2development or expansion begins.
Page 29, Line 3(b) In conducting the cumulative impacts analysis
Page 29, Line 4described in subsection (1)(a) of this section, a developer or
Page 29, Line 5operator shall contract with a third-party contractor
Page 29, Line 6selected by the department of public health and environment to
Page 29, Line 7perform the cumulative impacts analysis in a scientifically
Page 29, Line 8rigorous manner. The costs of the third-party contractor must
Page 29, Line 9be borne entirely by the developer or operator.
Page 29, Line 10(2) In reviewing, approving, denying, or amending a
Page 29, Line 11development permit application for a large-load data center
Page 29, Line 12that is in a disproportionately impacted community or is
Page 29, Line 13proposed to be in a disproportionately impacted community,
Page 29, Line 14including a development permit modification that would cause
Page 29, Line 15a data center in a disproportionately impacted community to
Page 29, Line 16become a large-load data center, the applicable local
Page 29, Line 17government shall consider the applicant's cumulative impacts
Page 29, Line 18analysis. If the local government finds that the large-load
Page 29, Line 19data center proposed by the application will have net negative
Page 29, Line 20cumulative impacts on a disproportionately impacted
Page 29, Line 21community, the local government shall consider if mitigation
Page 29, Line 22strategies described by the applicant are sufficient to avoid the
Page 29, Line 23negative impacts identified in the cumulative impacts analysis.
Page 29, Line 24The local government may consult with the department of
Page 29, Line 25public health and environment regarding the results of the
Page 29, Line 26cumulative impacts analysis and proposed mitigation strategies.
Page 29, Line 27In reviewing, approving, denying, or amending an application, the
Page 30, Line 1local government shall include a plain language summary of its
Page 30, Line 2determination.
Page 30, Line 3(3) (a) Prior to applying for a development permit for a
Page 30, Line 4large-load data center that is in a disproportionately impacted
Page 30, Line 5community or is proposed to be in a disproportionately impacted
Page 30, Line 6community, including a development permit modification that
Page 30, Line 7would cause a data center in a disproportionately impacted
Page 30, Line 8community to become a large-load data center, the large-load
Page 30, Line 9data center developer or large-load data center operator, as
Page 30, Line 10applicable, shall:
Page 30, Line 11(I) Host a minimum of three public hearings or comment
Page 30, Line 12periods at least sixty days prior to submitting the development
Page 30, Line 13permit application. At least one of the public hearings or
Page 30, Line 14comment periods must be held within the disproportionately
Page 30, Line 15impacted community where the developer or operator plans to
Page 30, Line 16operate the large-load data center or is currently operating
Page 30, Line 17the data center.
Page 30, Line 18(II) Schedule variable times of day and days of the week
Page 30, Line 19for opportunities for public input on the project, including at
Page 30, Line 20least one time on Saturday or Sunday, one time after 5 p.m., and
Page 30, Line 21one time before 12 noon;
Page 30, Line 22(III) Provide public notice at least thirty days before any
Page 30, Line 23public hearing or before the start of any comment period, which
Page 30, Line 24public notice must include the time, place, and location of the
Page 30, Line 25public hearing and a summary of the project and may be provided
Page 30, Line 26through several different outlets and locations, including:
Page 30, Line 27(A) Schools;
Page 31, Line 1(B) Health clinics;
Page 31, Line 2(C) Social media;
Page 31, Line 3(D) Social and activity clubs;
Page 31, Line 4(E) Local governments;
Page 31, Line 5(F) Tribal governments;
Page 31, Line 6(G) Religious or civic organizations;
Page 31, Line 7(H) Community-based environmental justice
Page 31, Line 8organizations; or
Page 31, Line 9(I) Other local services;
Page 31, Line 10(IV) Provide outreach materials translated into the top
Page 31, Line 11two languages spoken in the disproportionately impacted
Page 31, Line 12community where the developer or operator plans to develop or
Page 31, Line 13operate or is operating the large-load data center, which
Page 31, Line 14materials inform the disproportionately impacted community
Page 31, Line 15about opportunities to provide input on the project, the rights of
Page 31, Line 16the community, the possible outcomes of the project, and any
Page 31, Line 17upcoming public hearings or comment periods; and
Page 31, Line 18(V) Implement other best practices for outreach and
Page 31, Line 19engagement set forth in section 24-4-109 (3)(b).
Page 31, Line 20(b) During a public hearing or comment period described
Page 31, Line 21in this subsection (3), the large-load data center developer or
Page 31, Line 22large-load data center operator shall explicitly disclose the
Page 31, Line 23results of the cumulative impacts analysis conducted by a
Page 31, Line 24third-party contractor pursuant to subsection (1) of this
Page 31, Line 25section. The developer or operator shall also describe the
Page 31, Line 26efforts that the developer or operator will make to reduce
Page 31, Line 27anticipated negative impacts to the disproportionately impacted
Page 32, Line 1community or its environment from the proposed large-load
Page 32, Line 2data center project.
Page 32, Line 3(4) (a) If a large-load data center is proposed in a
Page 32, Line 4disproportionately impacted community or if an operator of a
Page 32, Line 5data center in a disproportionately impacted community that
Page 32, Line 6exists before the effective date of this section plans to expand
Page 32, Line 7the data center's peak load such that the data center will
Page 32, Line 8become a large-load data center, the developer or operator, as
Page 32, Line 9applicable, shall enter into a legally binding and publicly
Page 32, Line 10disclosed community benefit agreement with the
Page 32, Line 11disproportionately impacted community before the development
Page 32, Line 12or expansion begins.
Page 32, Line 13(b) (I) During community benefit agreement negotiations,
Page 32, Line 14the developer or operator shall consult with the local
Page 32, Line 15government with jurisdiction over the large-load data center
Page 32, Line 16or proposed large-load data center project and a coalition of
Page 32, Line 17at least three community-based organizations within a two-mile
Page 32, Line 18radius of the large-load data center or proposed large-load
Page 32, Line 19data center project. The developer or operator shall host a
Page 32, Line 20series of at least five meetings with key stakeholder groups
Page 32, Line 21identified by the local government and coalition. At least two
Page 32, Line 22of the meetings must offer the opportunity for public comment.
Page 32, Line 23The meetings must comply with the best practices for outreach
Page 32, Line 24and engagement set forth in section 24-4-109 (3)(b).
Page 32, Line 25(II) In negotiating a community benefit agreement, the
Page 32, Line 26parties shall consider:
Page 32, Line 27(A) The prioritization of disproportionately impacted
Page 33, Line 1communities through first-source hiring programs, revenue
Page 33, Line 2sharing, community program funding, community or public
Page 33, Line 3ownership requirements, and other state-initiated mechanisms;
Page 33, Line 4and
Page 33, Line 5(B) Regular equity impact assessments, protections for
Page 33, Line 6renters and small businesses, and public dashboards for
Page 33, Line 7disclosure of information deemed relevant by the coalition of
Page 33, Line 8community organizations described in subsection (4)(b)(I) of this
Page 33, Line 9section.
Page 33, Line 10(c) (I) A community benefit agreement should aim to avoid
Page 33, Line 11and mitigate negative impacts from the large-load data center,
Page 33, Line 12drive investments and services requested by disproportionately
Page 33, Line 13impacted communities, and support local workforce
Page 33, Line 14development.
Page 33, Line 15(II) A community benefit agreement may contemplate a
Page 33, Line 16community benefit fund tied to project scale, environmental and
Page 33, Line 17public health, long-term subsidies and monitoring, and
Page 33, Line 18supporting housing, broadband, health-care and child care
Page 33, Line 19centers, and community resilience.
Page 33, Line 20(d) A local government may determine appropriate
Page 33, Line 21penalties for noncompliance with a community benefit
Page 33, Line 22agreement.
Page 33, Line 2340-2.5-108. Labor standards.
Page 33, Line 24(1) A large-load data center operator shall:
Page 33, Line 25(a) Provide prevailing wages, as defined in section
Page 33, Line 2624-92-201 (6) and determined by the director of the department
Page 33, Line 27of personnel pursuant to section 24-92-205 (1), to employees that
Page 34, Line 1are fully employed, as defined in section 8-70-103 (12.5);
Page 34, Line 2(b) Participate in an apprenticeship program registered
Page 34, Line 3with the United States department of labor or a state
Page 34, Line 4apprenticeship agency recognized by the United States
Page 34, Line 5department of labor;
Page 34, Line 6(c) Require participation in the "OSHA 10" class or a class
Page 34, Line 7offered by the federal occupational safety and health
Page 34, Line 8administration comprised of substantially similar content;
Page 34, Line 9(d) Comply with any applicable workplace site safety plan
Page 34, Line 10requirements of the federal occupational safety and health
Page 34, Line 11administration; and
Page 34, Line 12(e) Not have a documented pattern of wage theft or
Page 34, Line 13misclassification of employees, as defined in section 8-72-114
Page 34, Line 14(2)(f).
Page 34, Line 15SECTION 3. Applicability. This act applies to conduct occurring
Page 34, Line 16on or after the effective date of this act.
Page 34, Line 17SECTION 4. Safety clause. The general assembly finds,
Page 34, Line 18determines, and declares that this act is necessary for the immediate
Page 34, Line 19preservation of the public peace, health, or safety or for appropriations for
Page 34, Line 20the support and maintenance of the departments of the state and state
Page 34, Line 21institutions.