House Bill 26-1124 Introduced

LLS NO. 26-0307.02 Jery Payne x2157
Second Regular Session
Seventy-fifth General Assembly
State of Colorado

House Sponsorship

DeGraaf,

Senate Sponsorship

(None),


House Committees

Energy & Environment

Senate Committees

No committees scheduled.


Strikethrough:
removed from existing law
Screen Reader Only:
all text indicated as strikethrough will begin as 'deleted from existing statue' and finish with 'end deletion'
All-caps or Bold and Italic:
added to existing law
Screen Reader Only:
all text indicated as all-caps or bold and italic will begin as 'added to existing law' and finish with 'end insertion'
Underline:
Senate Amendment
Highlight:
House Amendment

A Bill for an Act


Bill Summary

(Note: This summary applies to this bill as introduced and does not reflect any amendments that may be subsequently adopted. If this bill passes third reading in the house of introduction, a bill summary that applies to the reengrossed version of this bill will be available at http://leg.colorado.gov.)

The bill creates the Colorado electric grid resiliency task force (task force) to study the issue of grid resilience and to make recommendations to the governor and the general assembly. The task force is 18 members.

The president of the senate and the speaker of the house of representatives shall organize and call the first meeting of the task force by November 28, 2026. The task force meets at least once every month until it completes its duties, but the chair may call additional meetings. Upon request by the task force, the department of regulatory agencies shall provide office space, equipment, and staff services as necessary.

The task force has the following duties on a biennial basis:

The bill sets minimum technical standards for the assessment, plan, and recommendations.

A transmission-owning entity must participate in the task force assessment and provide any requested data. These entities may recover reasonable and prudent costs incurred to comply with the bill through rates, member assessments, or ordinary budgeting processes.

Owners or operators of covered transformers are required to file with the federal energy regulatory commission a report, marked as "Critical Energy/Electric Infrastructure Information". Standards are set for the report. Biennially, the public utilities commission must prepare a summary of the report and present it to the house of representatives energy and environment committee and the senate transportation and energy committee.

The public utilities commission must adopt rules requiring implementation of the highest-priority hardware-based mitigation measures identified by the task force unless equivalent protection is demonstrated.

The task force repeals on September 1, 2031. Before the repeal, it is scheduled for review under the sunset law.