A Bill for an Act
Page 1, Line 101Concerning local government permitting of wireless
Page 1, Line 102telecommunications facilities.
Bill Summary
(Note: This summary applies to this bill as introduced and does not reflect any amendments that may be subsequently adopted. If this bill passes third reading in the house of introduction, a bill summary that applies to the reengrossed version of this bill will be available at http://leg.colorado.gov/.)
Cell Phone Connectivity Interim Study Committee. The bill requires that an application by a telecommunications provider for the siting and construction of a new wireless telecommunications facility or for the substantial change of an existing wireless telecommunications facility (application) submitted to a local government is deemed approved by the local government if:
- The local government has not approved or rejected the application within 60 days after the application is submitted to the local government or conducted a pre-application meeting or other documented communication regarding the application, whichever is earlier (60-day time period);
- The telecommunications provider has provided all public notices required under applicable law; and
- The telecommunications provider has provided notice to the local government that the 60-day time period has lapsed and that the application is deemed approved.
- The telecommunications provider notifies the local government of the necessary removal, discontinuance, or replacement of the telecommunications equipment; and
- The removal, discontinuance, or replacement of the telecommunications equipment is not a substantial change to the facility.
A local government may toll the 60-day time period to allow the local government to make timely requests for information to complete an application. The 60-day time period may also be extended by mutual agreement of the telecommunications provider and the local government.
The bill also prohibits a local government from requiring a telecommunications provider that removes, discontinues, or replaces telecommunications equipment at an existing wireless telecommunications facility to file a new application or obtain additional permits if:
The bill takes effect on January 1, 2026.
Page 2, Line 1Be it enacted by the General Assembly of the State of Colorado:
Page 2, Line 2SECTION 1. In Colorado Revised Statutes, amend 29-27-401 as
Page 2, Line 3follows:
Page 2, Line 429-27-401. Legislative declaration. (1) The general assembly
Page 2, Line 5finds and declares that:
Page 2, Line 6(a) The permitting, construction, modification, maintenance, and
Page 2, Line 7operation of broadband facilities are critical to ensuring that all citizens
Page 2, Line 8in the state have true access to advanced technology and information;
Page 2, Line 9(b)
These Broadband facilities are critical to ensuring thatPage 2, Line 10businesses and schools throughout the state remain competitive in the
Page 3, Line 1global economy; and
Page 3, Line 2(c) The permitting, construction, modification, maintenance, and
Page 3, Line 3operation of
these broadband facilities, to the extent specificallyPage 3, Line 4addressed in this part 4, are declared to be matters of statewide concern
Page 3, Line 5and interest.
Page 3, Line 6(2) The general assembly further finds and declares that reliable
Page 3, Line 7wireless connectivity throughout the state:
Page 3, Line 8(a)
Small cell facilities often may be deployed most effectively inPage 3, Line 9
the public rights-of-way; and Is essential in supporting public safetyPage 3, Line 10operations and ensuring that the public is able to access
Page 3, Line 11life-saving assistance in times of crisis;
Page 3, Line 12(b)
Access to local government structures is essential to thePage 3, Line 13
construction and maintenance of wireless service facilities or broadbandPage 3, Line 14
facilities Is a significant driver of economic activity andPage 3, Line 15productivity for workers and organizations;
Page 3, Line 16(c) Is critical to providing access to information,
Page 3, Line 17educational resources, and job opportunities; and
Page 3, Line 18(d) Can help urban, historically underserved, and rural
Page 3, Line 19businesses improve workflow, while also amplifying visibility
Page 3, Line 20and sales for those businesses.
Page 3, Line 21(3) The general assembly further finds and declares that
Page 3, Line 22the efficient permitting of wireless facilities by local
Page 3, Line 23governments:
Page 3, Line 24(a) Has a significant public safety and economic benefit to
Page 3, Line 25Colorado; and
Page 3, Line 26(b) Is a matter of statewide concern.
Page 3, Line 27SECTION 2. In Colorado Revised Statutes, 29-27-402, amend
Page 4, Line 1(3) and (7); and add (3.1), (3.3), (3.7), and (6.2) as follows:
Page 4, Line 229-27-402. Definitions. As used in this part 4, unless the context
Page 4, Line 3otherwise requires:
Page 4, Line 4(3)
"Collocation "Collocate" means the mounting or installationPage 4, Line 5of broadband service equipment on a tower, building, or structure with
Page 4, Line 6existing broadband service equipment for the purpose of transmitting or
Page 4, Line 7receiving radio frequency signals for communications purposes.
Page 4, Line 8(3.1) "Collocation application" means an application for
Page 4, Line 9a collocation that results in a substantial change of an
Page 4, Line 10existing wireless telecommunications facility.
Page 4, Line 11(3.3) "Local government" has the same meaning as set
Page 4, Line 12forth in section 29-27-102 (3).
Page 4, Line 13(3.7) "Siting application" means an application for a new
Page 4, Line 14wireless service facility.
Page 4, Line 15(6.2) "Substantial change" has the same meaning as set
Page 4, Line 16forth in 47 CFR 1.6100 (b)(7), which implements the federal
Page 4, Line 17"Spectrum Act of 2012", 47 U.S.C. sec. 1455 (a).
Page 4, Line 18(7) "Wireless service facility" or "facility" means
a facility forPage 4, Line 19
the provision of wireless services; except that "wireless service facility"Page 4, Line 20
does not include coaxial or fiber-optic cable that is not immediatelyPage 4, Line 21
adjacent to, or directly associated with, a particular antenna equipmentPage 4, Line 22at a fixed location that enables wireless communications
Page 4, Line 23between user equipment and a communications network,
Page 4, Line 24including:
Page 4, Line 25(a) Macro and small cell facilities, transceivers,
Page 4, Line 26antennas, coaxial or fiber-optic cable, regular and backup
Page 4, Line 27power supplies, and comparable equipment, regardless of
Page 5, Line 1technological configuration, but does not include coaxial or
Page 5, Line 2fiber-optic cable that is not immediately adjacent to, or
Page 5, Line 3directly associated with, a particular antenna; and
Page 5, Line 4(b) The support structure or improvements on, under, or
Page 5, Line 5within which the equipment is collocated.
Page 5, Line 6SECTION 3. In Colorado Revised Statutes, repeal and reenact,
Page 5, Line 7with amendments, 29-27-403 as follows:
Page 5, Line 829-27-403. Deemed approval of facilities. (1) (a) A
Page 5, Line 9collocation application or siting application for a wireless
Page 5, Line 10service facility submitted to a local government is deemed
Page 5, Line 11approved by the local government if:
Page 5, Line 12(I) The local government has not approved or rejected
Page 5, Line 13the collocation application within ninety days after the
Page 5, Line 14applicant complies with the first procedural step required by the
Page 5, Line 15local government as part of its applicable regulatory review
Page 5, Line 16process or within ninety days after the applicant submits a
Page 5, Line 17collocation application if the local government's applicable
Page 5, Line 18regulatory process does not specify that first procedural step;
Page 5, Line 19except that the period for approval or rejection of a siting
Page 5, Line 20application that is not for a collocation or a small cell facility
Page 5, Line 21is one hundred twenty days;
Page 5, Line 22(II) The applicant has provided all public notices of the
Page 5, Line 23application required under applicable law; and
Page 5, Line 24(III) The applicant has provided notice to the local
Page 5, Line 25government that the applicable time period described in
Page 5, Line 26subsection (1)(a)(I) of this section has lapsed and that the
Page 5, Line 27application is deemed approved pursuant to this section.
Page 6, Line 1(b) A local government may toll the applicable period
Page 6, Line 2described in subsection (1)(a)(I) of this section to allow the
Page 6, Line 3local government to make timely requests for information to
Page 6, Line 4complete a collocation or siting application. The period may
Page 6, Line 5also be extended by mutual agreement of the applicant and the
Page 6, Line 6local government.
Page 6, Line 7(c) If a local government requires an applicant to obtain
Page 6, Line 8a traffic control plan or other permit related to obstruction
Page 6, Line 9of, or safety in, a public right-of-way before a collocation or
Page 6, Line 10siting application is approved, the applicant shall not commence
Page 6, Line 11the construction or substantial change of a wireless service
Page 6, Line 12facility pursuant to a collocation or siting application deemed
Page 6, Line 13approved pursuant to subsection (1)(a) of this section until the
Page 6, Line 14traffic control plan or other permit is obtained.
Page 6, Line 15(d) A local government may seek judicial review of the
Page 6, Line 16deemed approval of a collocation application or siting
Page 6, Line 17application pursuant to subsection (1)(a) of this section within
Page 6, Line 18thirty days after the notice described in subsection (1)(a)(III) of
Page 6, Line 19this section is provided to the local government.
Page 6, Line 20(e) A local government shall not:
Page 6, Line 21(I) Unreasonably withhold, condition, or delay approval
Page 6, Line 22of the issuance of a traffic control plan or other permit
Page 6, Line 23described in subsection (1)(c) of this section to delay the
Page 6, Line 24approval of a collocation application or siting application; or
Page 6, Line 25(II) Prohibit or unreasonably discriminate in favor of, or
Page 6, Line 26against, any technology in taking action on a collocation or
Page 6, Line 27siting application.
Page 7, Line 1(f) If a local government determines that a collocation
Page 7, Line 2or siting application is incomplete, the local government shall
Page 7, Line 3notify the applicant within thirty days after the submission of
Page 7, Line 4the application. The notification must be written, must clearly
Page 7, Line 5and specifically identify the missing documents or information
Page 7, Line 6that the applicant must submit to render the application
Page 7, Line 7complete, and must identify the specific regulation creating the
Page 7, Line 8requirement to provide the missing documents or information.
Page 7, Line 9Tolling of the period described in subsection (1)(a)(I) of this
Page 7, Line 10section begins on the date that the local government provides
Page 7, Line 11this notification and ends on the date that the applicant
Page 7, Line 12provides the requested information.
Page 7, Line 13(2) Except as otherwise expressly provided in this section,
Page 7, Line 14nothing in this section limits or affects the authority of a local
Page 7, Line 15government over the placement or construction of a wireless
Page 7, Line 16service facility.
Page 7, Line 17(3) Nothing in this section supersedes, nullifies, or
Page 7, Line 18otherwise alters generally applicable and nondiscriminatory
Page 7, Line 19building, electrical, fire, or other safety requirements.
Page 7, Line 20(4) Nothing in this section shall be interpreted or
Page 7, Line 21implemented in a way that prevents a local government from
Page 7, Line 22promptly acting on any other permit for use, occupation,
Page 7, Line 23installation, modification, repair, or operation in the public
Page 7, Line 24rights-of-way, including but not limited to permits for
Page 7, Line 25broadband facilities.
Page 7, Line 27SECTION 4. In Colorado Revised Statutes, add 29-27-405 as
Page 8, Line 1follows:
Page 8, Line 229-27-405. Facility equipment replacement. (1) A local
Page 8, Line 3government shall not require a collocation or siting
Page 8, Line 4application, or additional permits for the modification, removal,
Page 8, Line 5discontinuance, or replacement of a wireless service facility, or
Page 8, Line 6equipment associated therewith, if:
Page 8, Line 7(a) The owner or operator of the wireless service facility
Page 8, Line 8notifies the local government of the modification, removal,
Page 8, Line 9discontinuance, or replacement of the wireless service facility,
Page 8, Line 10or equipment associated with the wireless service facility; and
Page 8, Line 11(b) The modification, removal, discontinuance, or
Page 8, Line 12replacement does not amount to a substantial change to the
Page 8, Line 13wireless service facility.
Page 8, Line 14(2) Nothing in this section supersedes, nullifies, or
Page 8, Line 15otherwise alters generally applicable and nondiscriminatory
Page 8, Line 16building, electrical, fire, or other safety requirements.
Page 8, Line 17SECTION 5. In Colorado Revised Statutes, 38-5.5-104.5, amend
Page 8, Line 18(1) as follows:
Page 8, Line 1938-5.5-104.5. Use of local government entity structures.
Page 8, Line 20(1) Except as provided in subsection (2) of this section and subject to the
Page 8, Line 21requirements and limitations of this article 5.5,
sections 29-27-403 andPage 8, Line 22
29-27-404 part 4 of article 27 of title 29, and a local governmentPage 8, Line 23entity's police powers, a telecommunications provider or a broadband
Page 8, Line 24provider has the right to locate or collocate small cell facilities or small
Page 8, Line 25cell networks on the light poles, light standards, traffic signals, or utility
Page 8, Line 26poles in the rights-of-way owned by the local government entity; except
Page 8, Line 27that a small cell facility or a small cell network shall not be located or
Page 9, Line 1mounted on any apparatus, pole, or signal with tolling collection or
Page 9, Line 2enforcement equipment attached.
Page 9, Line 3SECTION 6. Act subject to petition - effective date -
Page 9, Line 4applicability. (1) This act takes effect at 12:01 a.m. on January 1, 2026;
Page 9, Line 5except that, if a referendum petition is filed pursuant to section 1 (3) of
Page 9, Line 6article V of the state constitution against this act or an item, section, or
Page 9, Line 7part of this act within such period, then the act, item, section, or part will
Page 9, Line 8not take effect unless approved by the people at the general election to be
Page 9, Line 9held in November 2026 and, in such case, will take effect on the date of
Page 9, Line 10the official declaration of the vote thereon by the governor.
Page 9, Line 11(2) This act applies to applications filed on or after the applicable
Page 9, Line 12effective date of this act.