A Bill for an Act
Page 1, Line 101Concerning local government permitting of wireless
Page 1, Line 102telecommunications facilities.
Bill Summary
(Note: This summary applies to this bill as introduced and does not reflect any amendments that may be subsequently adopted. If this bill passes third reading in the house of introduction, a bill summary that applies to the reengrossed version of this bill will be available at http://leg.colorado.gov/.)
Cell Phone Connectivity Interim Study Committee. The bill requires that an application by a telecommunications provider for the siting and construction of a new wireless telecommunications facility or for the substantial change of an existing wireless telecommunications facility (application) submitted to a local government is deemed approved by the local government if:
- The local government has not approved or rejected the application within 60 days after the application is submitted to the local government or conducted a pre-application meeting or other documented communication regarding the application, whichever is earlier (60-day time period);
- The telecommunications provider has provided all public notices required under applicable law; and
- The telecommunications provider has provided notice to the local government that the 60-day time period has lapsed and that the application is deemed approved.
- The telecommunications provider notifies the local government of the necessary removal, discontinuance, or replacement of the telecommunications equipment; and
- The removal, discontinuance, or replacement of the telecommunications equipment is not a substantial change to the facility.
A local government may toll the 60-day time period to allow the local government to make timely requests for information to complete an application. The 60-day time period may also be extended by mutual agreement of the telecommunications provider and the local government.
The bill also prohibits a local government from requiring a telecommunications provider that removes, discontinues, or replaces telecommunications equipment at an existing wireless telecommunications facility to file a new application or obtain additional permits if:
The bill takes effect on January 1, 2026.
This Unofficial Version Includes Committee
Amendments Not Yet Adopted on Second Reading
Page 2, Line 1Be it enacted by the General Assembly of the State of Colorado:
Page 2, Line 2SECTION 1. In Colorado Revised Statutes, amend 29-27-401 as
Page 2, Line 3follows:
Page 2, Line 429-27-401. Legislative declaration. (1) The general assembly
Page 2, Line 5finds and declares that:
Page 2, Line 6(a) The permitting, construction, modification, maintenance, and
Page 2, Line 7operation of broadband facilities are critical to ensuring that all citizens
Page 2, Line 8in the state have true access to advanced technology and information;
Page 2, Line 9(b)
These Broadband facilities are critical to ensuring thatPage 2, Line 10businesses and schools throughout the state remain competitive in the
Page 3, Line 1global economy; and
Page 3, Line 2(c) The permitting, construction, modification, maintenance, and
Page 3, Line 3operation of
these broadband facilities, to the extent specificallyPage 3, Line 4addressed in this part 4, are declared to be matters of statewide concern
Page 3, Line 5and interest.
Page 3, Line 6(2) The general assembly further finds and declares that reliable
Page 3, Line 7wireless connectivity throughout the state:
Page 3, Line 8(a)
Small cell facilities often may be deployed most effectively inPage 3, Line 9
the public rights-of-way; and Is essential in supporting public safetyPage 3, Line 10operations and ensuring that the public is able to access
Page 3, Line 11life-saving assistance in times of crisis;
Page 3, Line 12(b)
Access to local government structures is essential to thePage 3, Line 13
construction and maintenance of wireless service facilities or broadbandPage 3, Line 14
facilities Is a significant driver of economic activity andPage 3, Line 15productivity for workers and organizations;
Page 3, Line 16(c) Is critical to providing access to information,
Page 3, Line 17educational resources, and job opportunities; and
Page 3, Line 18(d) Can help urban, historically underserved, and rural
Page 3, Line 19businesses improve workflow, while also amplifying visibility
Page 3, Line 20and sales for those businesses.
Page 3, Line 21(3) The general assembly further finds and declares that
Page 3, Line 22the efficient permitting of wireless facilities by local
Page 3, Line 23governments:
Page 3, Line 24(a) Has a significant public safety and economic benefit to
Page 3, Line 25Colorado; and
Page 3, Line 26(b) Is a matter of statewide concern.
Page 3, Line 27SECTION 2. In Colorado Revised Statutes, 29-27-402, amend
Page 4, Line 1(3) and (7); and add (3.1), (3.3), (3.7), and (6.2) as follows:
Page 4, Line 229-27-402. Definitions. As used in this part 4, unless the context
Page 4, Line 3otherwise requires:
Page 4, Line 4(3)
"Collocation "Collocate" means the mounting or installationPage 4, Line 5of broadband service equipment on a tower, building, or structure with
Page 4, Line 6existing broadband service equipment for the purpose of transmitting or
Page 4, Line 7receiving radio frequency signals for communications purposes.
Page 4, Line 8(3.1) "Collocation application" means an application for
Page 4, Line 9a collocation that results in a substantial change of an
Page 4, Line 10existing wireless telecommunications facility.
Page 4, Line 11(3.3) "Local government" has the same meaning as set
Page 4, Line 12forth in section 29-27-102 (3).
Page 4, Line 13(3.7) "Siting application" means an application for a new
Page 4, Line 14wireless service facility.
Page 4, Line 15(6.2) "Substantial change" has the same meaning as set
Page 4, Line 16forth in 47 CFR 1.6100 (b)(7), which implements the federal
Page 4, Line 17"Spectrum Act of 2012", 47 U.S.C. sec. 1455 (a).
Page 4, Line 18(7) "Wireless service facility" or "facility" means
a facility forPage 4, Line 19
the provision of wireless services; except that "wireless service facility"Page 4, Line 20
does not include coaxial or fiber-optic cable that is not immediatelyPage 4, Line 21
adjacent to, or directly associated with, a particular antenna equipmentPage 4, Line 22at a fixed location that enables wireless communications
Page 4, Line 23between user equipment and a communications network,
Page 4, Line 24including:
Page 4, Line 25(a) Macro and small cell facilities, transceivers,
Page 4, Line 26antennas, coaxial or fiber-optic cable, regular and backup
Page 4, Line 27power supplies, and comparable equipment, regardless of
Page 5, Line 1technological configuration, but does not include coaxial or
Page 5, Line 2fiber-optic cable that is not immediately adjacent to, or
Page 5, Line 3directly associated with, a particular antenna; and
Page 5, Line 4(b) The support structure or improvements on, under, or
Page 5, Line 5within which the equipment is collocated.
Page 5, Line 6SECTION 3. In Colorado Revised Statutes, repeal and reenact,
Page 5, Line 7with amendments, 29-27-403 as follows:
Page 5, Line 829-27-403. Deemed approval of facilities. (1) (a) A
Page 5, Line 9collocation application or siting application for a wireless
Page 5, Line 10service facility submitted to a local government is deemed
Page 5, Line 11approved by the local government if:
Page 5, Line 12(I) The local government has not approved or rejected
Page 5, Line 13the collocation application within ninety days after the
Page 5, Line 14applicant submits a collocation application;except that the
Page 5, Line 15period for approval or rejection of a siting application that is
Page 5, Line 16not for a collocation or a small cell facility is one hundred
Page 5, Line 17twentydays after the applicant submits an application;
Page 5, Line 18(II) The applicant has provided all public notices of the
Page 5, Line 19application required under applicable law; and
Page 5, Line 20(III) The applicant has provided notice to the local
Page 5, Line 21government that the applicable time period described in
Page 5, Line 22subsection (1)(a)(I) of this section has lapsed and that the
Page 5, Line 23application is deemed approved pursuant to this section.
Page 5, Line 24(b) A local government may toll the applicable period
Page 5, Line 25described in subsection (1)(a)(I) of this section to allow the
Page 5, Line 26local government to make timely requests for information to
Page 5, Line 27complete a collocation or siting application. The period may
Page 6, Line 1also be extended by mutual agreement of the applicant and the
Page 6, Line 2local government.
Page 6, Line 3(c) If a local government requires an applicant to obtain
Page 6, Line 4a traffic control plan or other permit related to obstruction
Page 6, Line 5of, or safety in, a public right-of-way before a collocation or
Page 6, Line 6siting application is approved, the applicant shall not commence
Page 6, Line 7the construction or substantial change of a wireless service
Page 6, Line 8facility pursuant to a collocation or siting application deemed
Page 6, Line 9approved pursuant to subsection (1)(a) of this section until the
Page 6, Line 10traffic control plan or other permit is obtained.
Page 6, Line 11(d) A local government may seek judicial review of the
Page 6, Line 12deemed approval of a collocation application or siting
Page 6, Line 13application pursuant to subsection (1)(a) of this section within
Page 6, Line 14thirty days after the notice described in subsection (1)(a)(III) of
Page 6, Line 15this section is provided to the local government.
Page 6, Line 16(e) A local government shall not:
Page 6, Line 17(I) Unreasonably withhold, condition, or delay approval
Page 6, Line 18of the issuance of a traffic control plan or other permit
Page 6, Line 19described in subsection (1)(c) of this section to delay the
Page 6, Line 20approval of a collocation application or siting application; or
Page 6, Line 21(II) Prohibit or unreasonably discriminate in favor of, or
Page 6, Line 22against, any technology in taking action on a collocation or
Page 6, Line 23siting application.
Page 6, Line 24(f) If a local government determines that a collocation
Page 6, Line 25or siting application is incomplete, the local government shall
Page 6, Line 26notify the applicant within thirty days after the submission of
Page 6, Line 27the application. The notification must be written, must clearly
Page 7, Line 1and specifically identify the missing documents or information
Page 7, Line 2that the applicant must submit to render the application
Page 7, Line 3complete, and must identify the specific regulation creating the
Page 7, Line 4requirement to provide the missing documents or information.
Page 7, Line 5Tolling of the period described in subsection (1)(a)(I) of this
Page 7, Line 6section begins on the date that the local government provides
Page 7, Line 7this notification and ends on the date that the applicant
Page 7, Line 8provides the requested information.
Page 7, Line 9(2) Except as otherwise expressly provided in this section,
Page 7, Line 10nothing in this section limits or affects the authority of a local
Page 7, Line 11government over the placement or construction of a wireless
Page 7, Line 12service facility.
Page 7, Line 13(3) Nothing in this section supersedes, nullifies, or
Page 7, Line 14otherwise alters generally applicable and nondiscriminatory
Page 7, Line 15building, electrical, fire, or other safety requirements.
Page 7, Line 16(4) Nothing in this section shall be interpreted or
Page 7, Line 17implemented in a way that prevents a local government from
Page 7, Line 18promptly acting on any other permit for use, occupation,
Page 7, Line 19installation, modification, repair, or operation in the public
Page 7, Line 20rights-of-way, including but not limited to permits for
Page 7, Line 21broadband facilities.
Page 7, Line 22(5) Notwithstanding any other provision of this section,
Page 7, Line 23an applicant seeking to construct a facility within the exterior
Page 7, Line 24boundaries of an Indian reservation on land owned by the tribe
Page 7, Line 25must obtain the written consent of the applicable tribal
Page 7, Line 26government.
Page 8, Line 1SECTION 4. In Colorado Revised Statutes, add 29-27-405 as
Page 8, Line 2follows:
Page 8, Line 329-27-405. Facility equipment replacement. (1) A local
Page 8, Line 4government shall not require a collocation or siting
Page 8, Line 5application, or additional permits for the modification, removal,
Page 8, Line 6discontinuance, or replacement of a wireless service facility, or
Page 8, Line 7equipment associated therewith, if:
Page 8, Line 8(a) The owner or operator of the wireless service facility
Page 8, Line 9notifies the local government of the modification, removal,
Page 8, Line 10discontinuance, or replacement of the wireless service facility,
Page 8, Line 11or equipment associated with the wireless service facility; and
Page 8, Line 12(b) The modification, removal, discontinuance, or
Page 8, Line 13replacement does not amount to a substantial change to the
Page 8, Line 14wireless service facility.
Page 8, Line 15(2) Nothing in this section supersedes, nullifies, or
Page 8, Line 16otherwise alters generally applicable and nondiscriminatory
Page 8, Line 17building, electrical, fire, or other safety requirements.
Page 8, Line 18SECTION 5. In Colorado Revised Statutes, 38-5.5-104.5, amend
Page 8, Line 19(1) as follows:
Page 8, Line 2038-5.5-104.5. Use of local government entity structures.
Page 8, Line 21(1) Except as provided in subsection (2) of this section and subject to the
Page 8, Line 22requirements and limitations of this article 5.5,
sections 29-27-403 andPage 8, Line 23
29-27-404 part 4 of article 27 of title 29, and a local governmentPage 8, Line 24entity's police powers, a telecommunications provider or a broadband
Page 8, Line 25provider has the right to locate or collocate small cell facilities or small
Page 8, Line 26cell networks on the light poles, light standards, traffic signals, or utility
Page 8, Line 27poles in the rights-of-way owned by the local government entity; except
Page 9, Line 1that a small cell facility or a small cell network shall not be located or
Page 9, Line 2mounted on any apparatus, pole, or signal with tolling collection or
Page 9, Line 3enforcement equipment attached.
Page 9, Line 4SECTION 6. Act subject to petition - effective date -
Page 9, Line 5applicability. (1) This act takes effect at 12:01 a.m. on January 1, 2026;
Page 9, Line 6except that, if a referendum petition is filed pursuant to section 1 (3) of
Page 9, Line 7article V of the state constitution against this act or an item, section, or
Page 9, Line 8part of this act within such period, then the act, item, section, or part will
Page 9, Line 9not take effect unless approved by the people at the general election to be
Page 9, Line 10held in November 2026 and, in such case, will take effect on the date of
Page 9, Line 11the official declaration of the vote thereon by the governor.
Page 9, Line 12(2) This act applies to applications filed on or after the applicable
Page 9, Line 13effective date of this act.