Senate Committee of Reference Report

Committee on Transportation & Energy

Strikethrough:
removed from existing law
Screen Reader Only:
all text indicated as strikethrough will begin as 'deleted from existing statue' and finish with 'end deletion'
All-caps or Bold and Italic:
added to existing law
Screen Reader Only:
all text indicated as all-caps or bold and italic will begin as 'added to existing law' and finish with 'end insertion'

May 5, 2025

After consideration on the merits, the Committee recommends the following:

HB25-1292   be amended as follows, and as so amended, be referred to the Committee on Appropriations with favorable recommendation:

Page 1, Line 1Amend reengrossed bill, page 3, line 19, strike "sixty-nine" and

Page 1, Line 2substitute "one hundred fifteen".

Page 1, Line 3Page 5, strike lines 18 through 22 and substitute:

Page 1, Line 4"(III)  The constructability, access, and maintenance

Page 1, Line 5report must include mitigation strategies for potential impacts

Page 1, Line 6of the proposed high voltage line, as identified by the

Page 1, Line 7department in consultation with the Colorado energy office

Page 1, Line 8created in section 24-38.5-101 and other consulting agencies in

Page 1, Line 9the discretion of the department. Potential impacts include

Page 1, Line 10impacts to:

Page 1, Line 11(A)  Habitat, wildlife, and wildlife crossings;

Page 1, Line 12(B)  Communities; and

Page 1, Line 13(C)  Disproportionately impacted communities, as defined

Page 1, Line 14in section 24-4-109 (2)(b)(II).

Page 1, Line 15(IV) (A)  A mitigation strategy for an impact to a

Page 1, Line 16disproportionately impacted community, as outlined in a

Page 1, Line 17constructability, access, and maintenance report, must include

Page 1, Line 18community engagement that follows best practices for

Page 1, Line 19community engagement. The department shall review whether

Page 1, Line 20a transmission developer has followed best practices for

Page 1, Line 21community engagement. In its review, the department shall

Page 1, Line 22consider the recommendations outlined in the Colorado

Page 1, Line 23environmental justice action task force's 2022 final report of

Page 1, Line 24the task force, as defined in section 25-1-133 (1)(f).

Page 1, Line 25(B)  Community engagement activities that are consistent

Page 1, Line 26with regulations or requirements of the public utilities

Page 2, Line 1commission satisfy the requirements of this subsection (2)(b)(IV)

Page 2, Line 2for community engagement.".

Page 2, Line 3Renumber succeeding subparagraph accordingly.

Page 2, Line 4Page 9, line 10, strike "Colorado energy office and the".

Page 2, Line 5Page 9, line 14, strike "Colorado energy office and the".

Page 2, Line 6Page 9, line 16, strike "their websites" and substitute "its website".

Page 2, Line 7Page 9, line 17, after "department," insert "the Colorado energy

Page 2, Line 8office,".